Current Public Works Projects

Print
Press Enter to show all options, press Tab go to next option

Pioneer Creek Road Storm Damage Repairs:

Pioneer Creek Road will be repaired as a result of landside damage from severe winter storms in 2017.  This project includes constructing a retaining wall, placing the embankment, and paving approximately 100 feet of Pioneer Creek Road to restore existing facility use.  The project has started and is scheduled to be completed in November 2019.

 

Jackson Valley Road Hot Mix Asphalt Overlay Project:

Jackson Valley Road is an overlay project with approximately 2-inches of hot mix asphalt.  The project limits will begin east of the intersection of State Route 88 (West connection) and end at approximately (west of) Lake Amador Drive.  The project includes paving of various types of side access points and restriping Jackson Valley Road to match existing facility use and is expected to begin in the fall of 2019.

 

Bridge Replacement Project - 4 Bridges:

Bunker Hill Road Bridge: Completed

Fiddletown Road Bridge: The Fiddletown Road Bridge, constructed in 1923, is a 32.8-foot long, 2-lane concrete arch bridge that spans over North Fork Dry Creek.  The project is to remove the existing structure and reconstruct with a bridge to provide pedestrian and vehicle access.  Currently, the County is completing right-of-way and permitting.

 Old Amador Road Bridge: The Old Amador Road Bridge, constructed in 1925, is a 65-foot long, 2-span bridge that spans over Rancheria Creek.  The project is to remove the existing structure and reconstruct with a bridge to provide pedestrian and vehicle access.  Currently, the County is completing the environmental review and design.

Bell Road Bridge: The project will replace the existing structurally deficient bridge, constructed in 1925.  The roadway at the bridge will conform to the existing roadway at approximately 400-feet from each side of the bridge.  The new bridge would accommodate one 12-foot wide travel lane and two 2-foot wide shoulders.  Currently, the County is completing environmental review and design.

Carbondale Bridge over Willow Creek at Forest Home:

The County with Caltrans will replace Carbondale Road Bridge over Willow Creek.  The project is funded through a Federal Program (HBP) and local toll credits.  The project plans to replace the existing bridge with a new structure accommodating two 11-foot wide lanes, 2-foot wide shoulders and bridge railings, resulting in a wider bridge.  The roadway alignment would remain unchanged.  Along with a longer bridge, the roadway profile would be raised by approximately four (4) feet.  Currently, the County is completing right-of-way and permitting.

 

SR 88 Pine Grove Corridor Improvement Project:

The Pine Grove Corridor Improvement Project SR 88 will begin west of the existing Climax Road intersection, through the town of Pine Grove, and ending east of Tabeaud Road.  The project will be phased and some of the proposed project will include:

  • Adding eight foot shoulders to the north and south side of the highway west of the new Climax Road intersection to east of Tabeaud Road. 
  • Adding six foot sidewalks to the south side of the highway at Ridge Road intersection and start again before Irishtown Road. 
  • Adding sidewalks on both sides of SR 88 from Irishtown Road to the driveway entrance to Pine Grove Elementary School.  
  • Relocate the driveway exit of the Pine Grove Elementary School onto Volcano Road (instead of SR 88).  The entrance will remain unchanged.
  • Extend the westbound climbing lane to Tabeaud Road.
  • Turn pockets will be added at various locations, along the project limits and the two way left turn lane will be maintained from Ridge Road to Tabeaud Road.
  • Adding a traffic signal at three locations along SR 88 at:
    • Irishtown Road
    • Volcano Road
    • Tabeaud Road

 

 Completed Projects:

County Road Dig-Outs, Buckhorn Ridge Road and Pioneer Volcano Road:

Large and small sections of existing roadway along Buckhorn Ridge Road and Pioneer Volcano Road will be removed and replaced.  Traffic control will be implemented at the time of construction.  Tentative construction schedule is late August/ September 2019.

 

County Road Dig-Outs Project, Buena Vista Road and Stony Creek Road:

Large and small sections of existing roadway along Buena Vista Road and Stony Creek Road will be removed and replaced.  Traffic control will be implemented at the time of construction.  Construction has started and expected to be completed by October 2019..

 

Curran Road Hot Mix Asphalt Overlay Project:

Curran Road is an overlay project with approximately 2-inches of hot mix asphalt from approximately Post Mile 1.0 (west) to Camanche Parkway North (east).  The Project includes paving of various types of side access points and restriping Curran Road to match existing facility use.  The start date is September 16, 2019 and scheduled to be completed September 27, 2019.

 

Camanche Road Hot Mix Asphalt Overlay Project:

Camanche Road is an overlay project with approximately 2-inches of hot mix asphalt from approximately Curran Road (south) to Jackson Valley Road (north).  The Project includes paving of various types of side access points and restriping Camanche Road to match existing facility use.  The start date is September 16, 2019 and scheduled to be completed September 27, 2019.

 

Camanche Parkway North Hot Mix Asphalt Overlay Project:

Camanche Parkway North is an overlay project with approximately 2-inches of hot mix asphalt from approximately Lakeview Drive (west) to Camanche Road.  The Project includes paving of various types of side access points and restriping Camanche Parkway North to match existing facility use.  The project is scheduled to begin July 22, 2019 and end on August 9, 2019.  Traffic control will be implemented at the time of construction.

 

Shenandoah @ Fiddletown Road Intersection Improvements

 

 Ridge Road / New York Ranch Road Intersection Improvements

 

Countywide Turnouts / Widen  Shoulders Project -- View these turnout sites with Google Earth:

Shakeridge Road sites (6):  

 Fiddletown Road sites (4):

Shenandoah Road sites (4):

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer